ECB Wicket Specifications

The pitch markings will be in accordance with the governing bodies requirements

The outer dimensions of the artificial surface (pitch), shall be as detailed in the Table Below:-

TABLE : SURFACE DIMENSIONS

OUTDOORS

FACILITY

MINIMUM LENGTH

MINIMUM WIDTH

Match Play

30.00m

2.74m

Match Play Junior

22.00m

2.74m

Practise (Nets)

Batting 11.00m

2.74m

Bowling 8.00m

2.74m

(Ideal 10.00m)

Note:

10.00m 6 metres in front of stumps
4 metres behind the stumps
8.00m 5 metres in front of the stumps
4 metres behind the stumps

Practise Junior (Nets)
Unders 12 years

Batting 10.00m
Bowling 8.00m

2.00m

Centres of Excellence
Match

40.00m

3.66m

Centres of Excellence
Practise

Batting 17.00m
Bowling 13.00m

3.66m

INDOORS

Centres of Excellence
Match

40.00m

4.00m

Centres of Excellence
Practise

Batting 14.00m
Bowling 20.00m

3.66m

Practise (Nets)

Batting 11.00m

2.74m

Bowling 8.00m

2.74m

(Ideal 10.00m)

Note:

10.00m 6 metres in front of stumps
4 metres behind the stumps
8.00m 5 metres in front of the stumps
4 metres behind the stumps

Movable Matss
Match Practise

30.00m

2.00m

Practise

Batting 11.00m
Bowling

2.00m
2.00m

APPENDIX B

GUIDELINES

AGGREGATE (Where used in the base formation)

Where used within the structure aggregates are most suitable if they conform within the limited indicated below:

Type/name of Material:

Angular Interlocking frost resistant stone

Main range of particles:

3mm to 20mm

Particle shape

Angular

% of particles in required shape:

No less than 90%

UNBOUND MINERAL (interlocking of Waterbound)

Type/name of Material:

hard porous

Main range of particles:

3mm to 20mm

Particle shape

Angular

% of particles in required shape:

No less than 90%

SYNTHETIC TURF

Where used s it advisable they conform within the limits as appropriate for durability and the requirements below:

FIBRES:

UV Stabilised polypropylene and nylon

TURF DENSITY:

No less than 70,00 per sq mtr

PILE:
Note: In the pitch of the ball area

No less than 6mm. No more than 10mm pile. Lengths grater than 8mm must flatten rapidly. All pile lengths greater than 6mm must have flattened within a season's use (60games) to be no more than 6mm depth from the backing.
The pile must be non directional

TOTAL WEIGHT:

No less than 1300gms per sq. m

GRADIENTS:- (Non Mandatory)

When tested in accordance with the method of test indication in BS 7370 part 3 Appendix 5 using a 2 metre straight edge, a 1 metre spirit level, and a graduated wedge or rule in both longitudinal direction and across the width of the pitch, in four locations as indication on the drawing, the gradient should ideally be:-

Longitudinal:

No more than 1 in 80
No less than 1 in 300

Across the Width

No more than 1 in 50
No Less than 1 in 50

THICKNESS OF MATERIALS (Mandatory)

When tested in accordance with the method of test indicated in BS 7370 part 3 Appendix 7 or the method as submitted by the UK delegation to CEN for unbound mineral surfaces, the thickness must not vary by more than 10% from the average. This is specially important in the playing area.

MARKINGS (Mandatory)

When visually inspected an accordance with the Institute of Groundsmanship Performance Quality Standards all markings shall be in accordance with the rules of the game and clearly visible from a distance on 30 metres.

SURFACE WRINKLES (Mandatory)

When visually Inspected there must be no wrinkles in the surface or base formation components.

PERIMETER FIXING (Mandatory)

When examined the perimeter fixing must hold the surface and base formation components in position and must in no way be above or below the uniform plane established by the levels of evenness indicated for marrying in the surrounds to the perimeter of the pitch surface. Where stiff or hard edgings are used the upper side should not form a trip hazard between the surrounds of the surface of the pitch when the pitch has settled down.

Full criteria available if requested

 

ECBSpecifications1

PractiseWickets

MatchWickets

Renovations

diy

JMS Cricket Ltd, Parkside Works, Parkwood Street, Keighley BD21 4JP.
Tel: 01535 604777 Fax: 01535 606777
e-mail: sales@jmscricket.com

About Us | Cricket Covers | Sight Screens | Mobile Cages | Flat Sheets | Slip Cradles | Artificials | Misc.

FreeCounter